We build large-scale energy, infrastructure, logistics, and technology capacity. FNLT is the digital settlement layer for that work. It is not the whole company.

Focus

Physical build-out and operating base

Energy campus

Proposed utility-scale clean energy project in Barstow, California. Designed around a 100 MW solar photovoltaic facility with about 121,000 panels and about 175,000 MWh of estimated annual generation. The site covers about 580 acres.

Storage and capture

Battery energy storage is under evaluation for time-shifting, grid support, and dispatch flexibility. Direct air capture is being considered as another campus component. Neither is live infrastructure today.

Project scale

Current package estimates put solar EPC in the $83.2M to $88.5M range inside an overall project budget of about $115M.